Drainage on tennis and padel courts works differently from football pitches. The playing area is small, the surface is usually hard or semi-hard, and ball bounce reacts to the smallest level difference. Court drainage is therefore solved with the right surface slope, the right surface type and a well-planned water collection system around the court.
Acrylic-coated hard courts on concrete or asphalt, and most padel courts on concrete slabs, are in this group. Water runs off the surface, so the whole court is laid as a single plane, sloping from one side to the other or corner to corner.
Surfaces on porous asphalt or porous concrete, sand-filled artificial grass and clay courts let water pass partly or fully through. A crushed stone drainage layer and drain lines are added to the base, and the surface slope can be lower.
A crown in the middle of the court, sloping two ways, is not recommended: it disturbs the bounce and the surface wears along the ridge.
Run-off must be collected along the low side of the court:
Acrylic coatings need an even, impermeable base. Before coating, the court is flooded for a "flood test"; puddles left after 15–30 minutes are marked and filled with patching compound. On artificial grass courts, the perforated backing and the permeability of the base must work together.
SFS Engineering designs slope and drainage at the design stage of its tennis court and padel court projects and installs them with its own drainage products. For acrylic court care read our acrylic tennis court maintenance article.
For impermeable hard courts a single-plane slope of about 0.5–1% is recommended. Permeable systems can use a lower slope.
On outdoor padel courts the slab fall carries water to the low side and out through drainage gaps under the glass panels, into a perimeter channel.
Before coating, a flood test locates low spots, which are filled with patching compound. On existing courts the surface is recoated after local repairs.
On impermeable courts a channel along the low side where water collects is largely essential; otherwise water ponds at the court edge and on surrounding ground.
Get technical support for your project: SFS Engineering handles site survey, design, material selection and installation as a single contractor. Send us your dimensions and site details through our contact page and we will work out the right solution together.